Skip to content

By Darrin Crone on

Sir Nigel Gresley overhaul – update 42

In the workshop, progress is being made on the historic locomotive.

weeks commencing 8 July and 15 July 2019

The welded return cranks were collected from contractors and have been returned to York. The crank angle set-up jig has been used to mark the dummy cranks. We were very pleased with how well the jig performed.

Locomotive wheels in the workshop
The jig used to accurately identify the angle that the return cranks should be set.

The dummy cranks which will provide patterns for machining the real cranks have now been taken to be machined. There’s a considerable amount of machining work to be done on the cranks and the pressure is on to maintain the quality and accuracy so far achieved.

Locomotive parts in the workshop
On the back of the dummy return cranks the distance from the wheel centre is marked and the length of the crank from the centre of the pin.
Return cranks on the workshop floor.
The marked dummy return cranks will be used as patterns for the machining of the real return cranks to the correct dimensions.

The tender spring hangers are now being painted while the tender frames are receiving black gloss.

Locomotive tender frames painted black.
The tender frames are now painted to black gloss.

The repaired tender spring hangers were returned with NDT documentation covering the repaired areas. That left the hangers not requiring repair and the hook ends of all of them to NDT. So a last round of examinations was carried out, and a crack was found in one of them. The defect was ground out, as  surface defects can often be removed on components like these that show a lot of surface history. However, this was definitely a crack and extended into the hanger. It will require repair.

All of the new tender hornstay bolts have been completed with the drilling of the split pin holes.

Locomotive hornstay bolts on workshop bench.
A full set of new tender hornstay bolts.

The tender brasses continue to be scraped onto the journals. Unfortunately two have had to be reworked by contractors as they had excessive end float on the journal.

The tender front progresses with the lower two front plates trimmed, drilled and countersunk, while work has started grinding back the long weld that secured the streamlining to the original 1928 tender top. The exposed frame work at the front has been needle-gunned to remove as much of the corrosion as possible.

The butt strap used to increase the height of the front of the tender when streamlined will serve no purpose on the reconstructed tender but will be refitted. The strap was removed complete with all the rivet heads and these have been secured in the strap by welding.

In examining the front of the tender, we noticed that the corridor door appears to have moved and was not closing correctly. We know the tank doesn’t quite sit flat so to make sure we don’t build a twist into it, the beams the tank sits on were re-levelled. The packing the tank sits on was also rearranged to support the tank along the frame line. This didn’t seem to affect the position of the door much, so a string was run along the sides of the tank and we noticed that the tank side definitely bends in toward the front of the right side.

A prop was then put in and jacked out until the door lined up with the exposed framework in the tank. This required the cutting of the beam put to stabilise the front, which was put in before the front plate work was removed. The plates will be fitted to the current shape of the tank but final securing will take place after the tank is fastened down on to the frames, as if we make the front of the tank too rigid now we could end up deforming the frames.

A template has been made of the top section of the tender tank front, and was used to mark the location of the fixing holes. After the prop was put in, the template showed that the holes had shifted, with the tank much more rigid on the side opposite the corridor.

Front of locomtive tender in the workshop.
A pattern has been made of the plates required for the top of the tender front.

The piping team has been working on running the large diameter air supply pipe and putting in pipe clamps and supports to other pipe runs. Also in the tender frames some final work has been done to the TPWS conduit runs. The OTMR sensor enclosure was weld repaired and has now been drilled for the sensor bulkhead connection holes. The sensor bulkhead fittings have been cleared of contamination and the sensors have been checked. All sensors seem to be doing what they should but they will required formal calibration before refitting.

The middle tender vacuum cylinder bracket was positioned and the fixing holes were drilled through. The bracket has now been removed and the holes are being machined for the screws that go through the bracket and hold down the vacuum cylinder trunnions. New screws have also been machined.

The lower vestibule support rod housings are being welded to restore thickness lost to wear.

The first of the loco brake hangers has been rebushed and was clamped to the borer table to examine its straightness, as when on the loco some of the hangers appeared to be twisted. On the table compared to a large square there was some misalignment between the end bushes but it was very small, probably within tolerance. Attention then turned to the trailing pins in the loco frames. These are harder to get at than the others and do show more wear, probably being older. Due to the load on the pin they have worn out of shape and this may be the cause of the apparent twist seen when the loco came out of traffic. We have decided to replace these pins as they are too worn to be trued up and reused.

Work continues on the valve gear with the finishing the fitting of the pin in the reverser column crank. At the other end of the rod the lifting arms and nuts have been cleaned up by dressing out as much of the surface damage as we can without excessive removal of material, or character. The leading pins on the radius rods have also now been fitted and he is now on to the combination levers.

Locomotive parts in the workshop
The valve gear lifting arms, not at the correct angle, have now been overhauled to accept new pins.
Locomotive parts in the workshop
New pins have also been fitted to the valve gear radius rods.

Work on the slidebar bolts continues, with the right side being worked on.

The big end bearing pattern has now been received and was promptly sent to the foundry. They are a little concerned that the pattern won’t give us enough material on the bore to machine to the dimensions we need, so additional work will be required on the pattern before casting.

The strip down, clean and examination of the cods mouth door operating gear continues.

At Llangollen the superheater header is now successfully fitted and has been hydraulically tested in position. This means work can now commence on fitting the superheater elements.

View inside a locomotive boiler.
The superheater header in place and being pressure tested.

This is the 41st update—you can read all the previous instalments here.

Leave a comment

Your email address will not be published. Required fields are marked *